Roads24LB0109

CONCRETING OF BRGY. SUMIMAO FMR PHASE III, BRGY. SUMIMAO, PAQUIBATO DISTRICT, DAVAO CITY

CONCRETING OF BRGY. SUMIMAO FMR PHASE III, BRGY. SUMIMAO, PAQUIBATO DISTRICT, DAVAO CITY is a DPWH-tracked public work in Davao City DEO, Region XI. Reported contract value: ₱14,774,425.56. Status: Past target date (DPWH On-Going). Contractor on record: ROSBILL CONST AND SUPPLY. Figures trace to dpwh.

Davao City DEO, Region XI
Region: Region XI

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 78%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure, Barangay Mayo, Mati City, Davao Oriental
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Davao City DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

4. Implementation

Contract Amount

₱14,774,425.56

Progress

Past target date (DPWH On-Going)

Start Date

September 9, 2024

Target End

February 4, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.