Buildings and Facilities18LC0213

CONSTRUCTION OF 2 STY 6 CL SCHOOL BUILDING @ LA PAZ NHS,CARMEN,DAVAO DEL NORTE

CONSTRUCTION OF 2 STY 6 CL SCHOOL BUILDING @ LA PAZ NHS,CARMEN,DAVAO DEL NORTE is a DPWH-tracked public work in Davao del Norte DEO, Region XI. Reported contract value: ₱15,572,997.93. Status: Reported complete (DPWH). Contractor on record: FIVE MASSIVE INFRA. Figures trace to dpwh.

Davao del Norte DEO, Region XI
Region: Region XI

Money Trail

1. Appropriation

GAA FY2018 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

209 projects · ₱1.0B total · 0 flags

4. Implementation

Contract Amount

₱15,572,997.93

Progress

Reported complete (DPWH)

Start Date

December 27, 2018

Target End

June 4, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.