Buildings and Facilities18LC0211

CONSTRUCTION OF 2 STY 10 CL SCHOOL BUILDING @ ESPERANZA ES,STO.TOMAS,DAVAO DEL NORTE

CONSTRUCTION OF 2 STY 10 CL SCHOOL BUILDING @ ESPERANZA ES,STO.TOMAS,DAVAO DEL NORTE is a DPWH-tracked public work in Davao del Norte DEO, Region XI. Reported contract value: ₱28,476,100.96. Status: Reported complete (DPWH). Contractor on record: DANIMERH CONST. Figures trace to dpwh.

Davao del Norte DEO, Region XI
Region: Region XI

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2018 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱28,476,100.96

Progress

Reported complete (DPWH)

Start Date

December 27, 2018

Target End

July 19, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.