GAA 2024 DOH HFEP24N00224

DOH HEALTH FACILITIES ENHANCEMENT PROGRAM (HFEP) LGU HOSPITALS-AGUSAN DEL NORTE PROVINCIAL HOSPITAL, AGUSAN DEL NORTE

DOH HEALTH FACILITIES ENHANCEMENT PROGRAM (HFEP) LGU HOSPITALS-AGUSAN DEL NORTE PROVINCIAL HOSPITAL, AGUSAN DEL NORTE is a DPWH-tracked public work in Region XIII, Region XIII. Reported contract value: ₱49,697,532.68. Status: Past target date (DPWH On-Going). Contractor on record: REYROSE CONST. Figures trace to dpwh.

Region XIII, Region XIII
Region: Region XIII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2024 GAA. DBM GAA FY2024

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱49,697,532.68

Progress

Past target date (DPWH On-Going)

Start Date

February 7, 2025

Target End

February 1, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.