Buildings and Facilities18HB0180

CONSTRUCTION AND COMPLETION OF 3 STOREY - 6 CLASSROOMS, CAMBUYO HIGH SCHOOL, GARCIA-HERNANDEZ, BOHOL

CONSTRUCTION AND COMPLETION OF 3 STOREY - 6 CLASSROOMS, CAMBUYO HIGH SCHOOL, GARCIA-HERNANDEZ, BOHOL is a DPWH-tracked public work in Bohol 3rd DEO, Region VII. Reported contract value: ₱13,254,960.87. Status: Reported complete (DPWH). Contractor on record: ALGAMON CONST CORP FORMERLY: ALGAMON CONST. Figures trace to dpwh.

Bohol 3rd DEO, Region VII
Region: Region VII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Manao River Control, West Poblacion Poblacion, Garcia-Hernandez, Bohol
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROI-18-0000694

₱0.00 · FY2018

Released to Bonuan Boquig National High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱13,254,960.87

Progress

Reported complete (DPWH)

Start Date

July 31, 2018

Target End

December 27, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.