Rehabilitation / Major Repair of Drainage Structure22DC0029

Rehabilitation of Line Canal in Tanauan City, Batangas

Rehabilitation of Line Canal in Tanauan City, Batangas is a DPWH-tracked public work in CITY OF TANAUAN (BATANGAS), BATANGAS, Region IV-A. Reported contract value: ₱4,823,615.60. Status: Reported complete (DPWH). Contractor on record: JERIS CONST AND SUPPLY. Figures trace to sumbong.

CITY OF TANAUAN (BATANGAS), BATANGAS, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures along Tangisan to Takad River, Brgy. San Isidro, Batangas City, Batangas
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002895

₱1,037,658,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0010998

₱100,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003021

₱10,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIVA-22-0006164

₱5,000,000.00 · FY2022

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

153 projects · ₱852.3M total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, TANAUAN CITY-STO. TOMAS DIVERSION ROAD VIA SAMPALOCAN ROAD, BATANGAS

Batangas 3rd DEO, Region IV-A

2025₱67.7M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM - TRIP), SAN PEDRO - STA. CRUZ ECOTOURISM ROAD LEADING TO NATIONAL SHRINE OF ST. PADRE PIO, ST

Batangas 3rd DEO, Region IV-A

2023₱49.0M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF CLASSROOMS BATCH 1, FOUR STOREY TWENTY CLASSROOM, MALVAR NATIONAL HIGH SCHOOL, MALVA

Batangas 3rd DEO, Region IV-A

2018₱44.8M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS, SAN PEDRO-STA. CRUZ ECOTOURISM ROAD LEADING TO NATIONAL SHRINE OF ST. PADRE PIO, STO. TOMAS, BATANGAS

Batangas 3rd DEO, Region IV-A

2020₱41.5M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - TERTIARY ROADS, TALISAY-LAUREL-AGONCILLO RD

Batangas 3rd DEO, Region IV-A

2022₱34.3M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT - ROAD WIDENIND - TERTIARY ROADS, LIPA - BALETE RD

Batangas 3rd DEO, Region IV-A

2021₱28.2M
Reported complete (DPWH)
View all 153 projects →

4. Implementation

Contract Amount

₱4,823,615.60

Progress

Reported complete (DPWH)

Start Date

February 4, 2022

Target End

October 1, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.