Bridges17HG0069

RETROFITTING/STRENGTHENING OF RONDA BRIDGE (B00430CB)

RETROFITTING/STRENGTHENING OF RONDA BRIDGE (B00430CB) is a DPWH-tracked public work in Cebu 2nd DEO, Region VII. Reported contract value: ₱2,675,860.09. Status: Reported complete (DPWH). Contractor on record: VSP STRUCTURE VENTURES CORP FORMERLY: VIRLO CONST. Figures trace to dpwh.

Cebu 2nd DEO, Region VII
Region: Region VII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure of Dumlog River Dumlog, Sibonga Cebu
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROI-17-0000992

₱7,024,000.00 · FY2017

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

138 projects · ₱3.5B total · 4 flags

Other projects by this contractor

No sat.

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONST/ REHAB OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG COTCOT RIVER, PHASE 2, LILOAN, CEBU

Region VII, Region VII

2025₱154.3M
Past target date (DPWH On-Going)
No sat.

OO2: FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG COTCOT RIVER (DOWNSTREAM), LILOAN, CEBU

Cebu 5th DEO, Region VII

2025₱144.7M
Past target date (DPWH On-Going)

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG COTCOT RIVER, COMPOSTELA, CEBU

Cebu 5th DEO, Region VII

2024₱140.2M
Reported complete (DPWH)
No sat.

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM- CONST./MAINT. OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONST. OF FLOOD MITIGATION RIVERBANK FACILITIES ALONG CANSAGA RIVER, PACKAGE I, GARING, CONSOLACION, CEBU

Cebu 6th DEO, Region VII

2025₱135.0M
Past target date (DPWH On-Going)

Construction of Flood Control Structure along Bagatayam River, Sogod, Cebu

SOGOD (CEBU), CEBU, Region VII

2023₱106.1M
Reported complete (DPWH)
No sat.

CSSP: BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY JUBAY, LILOAN, CEBU

Cebu 5th DEO, Region VII

2025₱99.0M
Past target date (DPWH On-Going)
View all 138 projects →

4. Implementation

Contract Amount

₱2,675,860.09

Progress

Reported complete (DPWH)

Start Date

March 20, 2017

Target End

May 4, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.