GAA 2025 SSP25KC0023

INSTALLATION/APPLICATION OF ROAD SAFETY FACILITIES (PAVEMENT MARKINGS, ROAD SIGNS) ALONG SAYRE HIGHWAY - K1440+000-K1444+800, K1447+650-K1454+000, K1456+800-K1458+200, K1459+000-K1463+000, K1463+850-K1466+000, K1467+200-K1468+000, K1471+000-K1472+000, MA

INSTALLATION/APPLICATION OF ROAD SAFETY FACILITIES (PAVEMENT MARKINGS, ROAD SIGNS) ALONG SAYRE HIGHWAY - K1440+000-K1444+800, K1447+650-K1454+000, K1456+800-K1458+200, K1459+000-K1463+000, K1463+850-K1466+000, K1467+200-K1468+000, K1471+000-K1472+000, MA is a DPWH-tracked public work in Bukidnon 3rd DEO, Region X. Reported contract value: ₱32,786,612.10. Status: Reported complete (DPWH). Contractor on record: VEN RAY CONST CORP. Figures trace to dpwh.

Bukidnon 3rd DEO, Region X
Region: Region X

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Siloo River, Barangay Siloo, Malitbog, Bukidnon
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Bukidnon 3rd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

4. Implementation

Contract Amount

₱32,786,612.10

Progress

Reported complete (DPWH)

Start Date

February 7, 2025

Target End

April 9, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.