LOCAL INFRASTRUCTURE PROGRAM, CONCRETING OF BARANGAY ROAD, BARANGAY JANGAN, BALUD, MASBATE 2ND LD, B

LOCAL INFRASTRUCTURE PROGRAM, CONCRETING OF BARANGAY ROAD, BARANGAY JANGAN, BALUD, MASBATE 2ND LD, B is a DPWH-tracked public work in Masbate 2nd DEO, Region V. Reported contract value: ₱2,822,934.97. Status: Reported complete (DPWH). Contractor on record: SHA SHA LUMBER. Figures trace to dpwh.

Masbate 2nd DEO, Region V
Region: Region V

Money Trail

1. Appropriation

GAA FY2016 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱2,822,934.97

Progress

Reported complete (DPWH)

Start Date

February 16, 2016

Target End

March 6, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.