Roads17K00069

CONST. OF BY-PASSES/DIVERSION ROADS,GINGOOG BY-PASS RD INCL. ROW,MIS.OR.1ST LD

CONST. OF BY-PASSES/DIVERSION ROADS,GINGOOG BY-PASS RD INCL. ROW,MIS.OR.1ST LD is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱67,434,111.91. Status: Reported complete (DPWH). Contractor on record: C'ZARLES CONST. Figures trace to dpwh.

Region X, Region X
Region: Region X

Money Trail

1. Appropriation

GAA FY2017 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱67,434,111.91

Progress

Reported complete (DPWH)

Start Date

May 31, 2017

Target End

January 3, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.