Flood Control and Drainage16FB0061

CONST./REHAB. OF FC MITIGATION FACILITIES ALONG MAJOR RIVER BASINS AND PRINCIPAL RIVERS-YAWA/BASUD/QUIRANGAY RIVER BASIN-ARIMBAY RC PROJ., PRINCIPAL RIVERS-YAWA/BASUD/QUIRANGAY RIVER BASIN-ARIMBAY RC PROJECT, STA.0+160- STA. 0+390 (W/ EXCEP.),LEG CITY

CONST./REHAB. OF FC MITIGATION FACILITIES ALONG MAJOR RIVER BASINS AND PRINCIPAL RIVERS-YAWA/BASUD/QUIRANGAY RIVER BASIN-ARIMBAY RC PROJ., PRINCIPAL RIVERS-YAWA/BASUD/QUIRANGAY RIVER BASIN-ARIMBAY RC PROJECT, STA.0+160- STA. 0+390 (W/ EXCEP.),LEG CITY is a DPWH-tracked public work in Albay 2nd DEO, Region V. Reported contract value: ₱13,328,800.45. Status: Reported complete (DPWH). Contractor on record: E A SANCHO CONST INC FORM E A SANCHO CONST. Figures trace to dpwh.

Albay 2nd DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱29,956,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitaionof Flood Control System along Busay River (Left Side), Daraga, Albay
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXII-16-0035504

₱259,000.00 · FY2016

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

113 projects · ₱3.8B total · 0 flags

Other projects by this contractor

View all 113 projects →

4. Implementation

Contract Amount

₱13,328,800.45

Progress

Reported complete (DPWH)

Start Date

July 14, 2016

Target End

October 23, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.