GAA 2023 OO-223FF0030

002:FLOOD MANAGEMENT PROGRAM CONST. /MAINT. OF FLOOD MITIGATION STRUCTURES & DRAINAGE SYSTEM CONST. OF BOMBON FLOOD CONTROL BOMBON CAMARINES SUR

002:FLOOD MANAGEMENT PROGRAM CONST. /MAINT. OF FLOOD MITIGATION STRUCTURES & DRAINAGE SYSTEM CONST. OF BOMBON FLOOD CONTROL BOMBON CAMARINES SUR is a DPWH-tracked public work in Camarines Sur 3rd DEO, Region V. Reported contract value: ₱48,442,389.73. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: ST BERNARDINE CONST & ENT FOR ST. Figures trace to dpwh.

Camarines Sur 3rd DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Bombon Flood Control, Bombon, Camarines Sur
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Camarines Sur 3rd DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱48,442,389.73

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

May 3, 2023

Target End

April 5, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.