CONCRETING/CONSTRUCTION OF BRGY. TOLON- BRGY. BIRAYAN - BRGY. NILABO FMR

CONCRETING/CONSTRUCTION OF BRGY. TOLON- BRGY. BIRAYAN - BRGY. NILABO FMR is a DPWH-tracked public work in Zamboanga del Norte 1st DEO, Region IX. Reported contract value: ₱7,680,506.04. Status: Reported complete (DPWH). Contractor on record: MONTPHIL CONST CORP. Figures trace to dpwh.

Zamboanga del Norte 1st DEO, Region IX
Region: Region IX

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-C-19-0011919

₱716,783.00 · FY2019

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱7,680,506.04

Progress

Reported complete (DPWH)

Start Date

December 13, 2019

Target End

March 28, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.