Flood Control and Drainage24OE0175

REHABILITATION OF DRAINAGE SYSTEM ALONG MALABON ST., MANILA

REHABILITATION OF DRAINAGE SYSTEM ALONG MALABON ST., MANILA is a DPWH-tracked public work in North Manila DEO, National Capital Region. Reported contract value: ₱98,380,671.55. Status: Past target date (DPWH On-Going). Contractor on record: E M CUERPO INC. Figures trace to dpwh.

North Manila DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱12,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Estero de Binondo, Barangay 281, Manila City
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

North Manila DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

Construction Projects

₱95,930,210.35 · E.M. CUERPO .

Contractor

86 projects · ₱10.2B total · 0 flags

Other projects by this contractor

REHABILITATION OF DIKE SYSTEM ALONG SOLSONA RIVER (BREACHED AND ERODED DIKE, LEFT AND RIGHT BANK), LAOAG RIVER BASIN FLOOD CONTROL AND SABO PROJECT

Flood Control Management Cluster, Central Office

2017₱669.3M
Reported complete (DPWH)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS-CAMARINES SUR EXPRESSWAY (PACKAGE 4), SAN FERNANDO-MINALABAC, CAMARINES SUR(2ND LEGISLATIVE DISTRICT)

Region V, Region V

2022₱482.5M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - EVACUATION CENTERS/QUARANTINE FACILITIES/PUBLIC HEALTH FACILITIES - CONSTRUCTION (COMPLETION) OF EASTERN VISAYAS MEDICAL CENTER, CANCER CENTER, TACLOBAN CITY

Region VIII, Region VIII

2024₱482.2M
Past target date (DPWH On-Going)
No sat.

RAISING OF FOLDER DIKE INCLUDING SLOPE PROTECTION WORKS (PHASE 4: STA 2+030 TO STA. 2+530, PHASE 5: STA. 5+720 TO STA. 5+200, PHASE 6) BRGY. DAMPALIT, MALABON CITY

Flood Control Management Cluster, Central Office

2017₱284.5M
Past target date (DPWH On-Going)
No sat.

CLUSTER 5: PROJECT 1. BUILDINGS AND OTHER STRUCTURES - MULTIPURPOSE/FACILITIES - NATIONAL BUILDING PROGRAM - CONSTRUCTION OF THREE-STOREY BUILDING, DPWH REGIONAL OFFICE VIII, EQUIPMENT MANAGEMENT DIVISION, PHASE II, BARANGAY PAWING, PALO, LEYTE; PROJECT 2

Region VIII, Region VIII

2023₱277.7M
Past target date (DPWH On-Going)
No sat.

REHABILITATION OF FLOOD CONTROL, PAGSANGA-AN RIVER, ORMOC CITY

Region VIII, Region VIII

2024₱274.3M
Past target date (DPWH On-Going)
View all 86 projects →

4. Implementation

Contract Amount

₱98,380,671.55

Progress

Past target date (DPWH On-Going)

Start Date

February 21, 2024

Target End

May 3, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.