Roads18EF0045

ROAD UPGRADING (UNPAVED TO PAVED) OF CULANDANUM-PANALINGAAN CROSS COUNTRY ROAD CHAINAGE 14869-CHAINAGE 16169/CHAINAGE 16210-CHAINAGE 16442/CHAINAGE 18680-CHAINAGE20009, RIZAL, PALAWAN

ROAD UPGRADING (UNPAVED TO PAVED) OF CULANDANUM-PANALINGAAN CROSS COUNTRY ROAD CHAINAGE 14869-CHAINAGE 16169/CHAINAGE 16210-CHAINAGE 16442/CHAINAGE 18680-CHAINAGE20009, RIZAL, PALAWAN is a DPWH-tracked public work in Palawan 2nd DEO, Region IV-B. Reported contract value: ₱71,027,381.35. Status: Reported complete (DPWH). Contractor on record: KEILANA RESOURCE AND DEVELOPMENT CORP. Figures trace to dpwh.

Palawan 2nd DEO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Iraan Flood Control Structure at Rizal, Palawan
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-18-0005523

₱0.00 · FY2018

Released to Division of Palawan (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱71,027,381.35

Progress

Reported complete (DPWH)

Start Date

March 14, 2018

Target End

February 24, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.