Flood Control and Drainage17DN0042

REHABILITATION WITH SLOPE PROTECTION OF DIVERSION CHANNEL, PHASE 2, BRGY. SAN JUAN, TAYTAY, RIZAL

REHABILITATION WITH SLOPE PROTECTION OF DIVERSION CHANNEL, PHASE 2, BRGY. SAN JUAN, TAYTAY, RIZAL is a DPWH-tracked public work in Rizal 1st DEO, Region IV-A. Reported contract value: ₱19,569,629.23. Status: Reported complete (DPWH). Contractor on record: C F TRINIDAD CONST AND SUPPLIES CORP FOR 9199. Figures trace to dpwh.

Rizal 1st DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

GAA FY2017 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱19,569,629.23

Progress

Reported complete (DPWH)

Start Date

February 23, 2017

Target End

September 20, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.