GAA 2025 SSP25ME0084

CONSTRUCTION OF MAASIM LEVEL III WATER SYSTEM PHASE II, MAASIM, SARANGANI PROVINCE

CONSTRUCTION OF MAASIM LEVEL III WATER SYSTEM PHASE II, MAASIM, SARANGANI PROVINCE is a DPWH-tracked public work in Sarangani DEO, Region XII. Reported contract value: ₱23,958,890.18. Status: Past target date (DPWH On-Going). Contractor on record: KGD BUILDERS INC. Figures trace to dpwh.

Sarangani DEO, Region XII
Region: Region XII

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Maasim Flood Mitigation Structure at Brgy. Poblacion and Brgy. Colon, Maasim, Sarangani Province
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Sarangani DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

4. Implementation

Contract Amount

₱23,958,890.18

Progress

Past target date (DPWH On-Going)

Start Date

August 7, 2025

Target End

June 2, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.