Roads20LC0012

TAGUM CITY DIVERSION ROAD, K1458+195 - K1458+750

TAGUM CITY DIVERSION ROAD, K1458+195 - K1458+750 is a DPWH-tracked public work in Davao del Norte DEO, Region XI. Reported contract value: ₱28,490,660.00. Status: Reported complete (DPWH). Contractor on record: DBR CONST CORP FORMERLY: D B RAVELO CONST. Figures trace to dpwh.

Davao del Norte DEO, Region XI
Region: Region XI

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Lasang River Flood Control (Upstream of Lasang Bridge), Panabo, Davao del Norte
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Davao del Norte DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

4. Implementation

Contract Amount

₱28,490,660.00

Progress

Reported complete (DPWH)

Start Date

December 18, 2020

Target End

November 17, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.