Buildings and Facilities18MG0105

CONSTRUCTION OF MULTI-PURPOSE BUILDING (GYM), PUROK BUMANAAG, BRGY. ZONE III, KORONADAL CITY, SOUTH COTABATO

CONSTRUCTION OF MULTI-PURPOSE BUILDING (GYM), PUROK BUMANAAG, BRGY. ZONE III, KORONADAL CITY, SOUTH COTABATO is a DPWH-tracked public work in South Cotabato 2nd DEO, Region XII. Reported contract value: ₱2,367,506.72. Status: Reported complete (DPWH). Contractor on record: MIGO CONST. Figures trace to dpwh.

South Cotabato 2nd DEO, Region XII
Region: Region XII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱10,200,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Sinawal River bank protection, Sta.0+000-Sta. 0+050, Brgy. Labangal, General Santos City, South Cotabato
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-E-18-0012182

₱40,000.00 · FY2018

Released to Regional Office - IVA (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

158 projects · ₱846.8M total · 0 flags

4. Implementation

Contract Amount

₱2,367,506.72

Progress

Reported complete (DPWH)

Start Date

April 25, 2018

Target End

August 7, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.