Construction of Flood Mitigation Structure24CC0168

Construction of Reinforced Concrete Flood Control Structure along Balagtas River, Barangay Panginay (Sitio Sulok), Balagtas, Bulacan

Construction of Reinforced Concrete Flood Control Structure along Balagtas River, Barangay Panginay (Sitio Sulok), Balagtas, Bulacan is a DPWH-tracked public work in BALAGTAS (BIGAA) (BULACAN), BULACAN, Region III. Reported contract value: ₱78,163,573.63. Status: Reported complete (DPWH). Contractor on record: JB CONST AND SUPPLY INC FORMERLY:JB CONST AND SUPPLY. Figures trace to sumbong.

BALAGTAS (BIGAA) (BULACAN), BULACAN, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 93%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Balagtas River, Barangay San Juan, Purok 4 - Purok 5, Balagtas, Bulacan
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0007285

₱1,480,000.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0005755

₱1,178,933.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0017916

₱440,428.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0007286

₱137,000.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0005756

₱95,671.00 · FY2024

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱78,163,573.63

Progress

Reported complete (DPWH)

Start Date

February 28, 2024

Target End

October 24, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.