Roads24EH0068

CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG SIBUYAN CIRCUMFERENTIAL ROAD, K0047+134.13 - K0047+856.55 R/S (ACTUAL), K0047+144.13 - K0047+866.55 R/S (RBIA), SIBUYAN ISLAND, ROMBLON

CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG SIBUYAN CIRCUMFERENTIAL ROAD, K0047+134.13 - K0047+856.55 R/S (ACTUAL), K0047+144.13 - K0047+866.55 R/S (RBIA), SIBUYAN ISLAND, ROMBLON is a DPWH-tracked public work in Romblon DEO, Region IV-B. Reported contract value: ₱15,371,300.00. Status: Reported complete (DPWH). Contractor on record: MT GUITING-GUITING CONST 17412. Figures trace to dpwh.

Romblon DEO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Canlumay Flood Control Structure, Odiongan, Romblon
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Romblon DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

4. Implementation

Contract Amount

₱15,371,300.00

Progress

Reported complete (DPWH)

Start Date

June 7, 2024

Target End

November 17, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.