Roads16H00051

REHABILITATION/RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE SECONDARY ROADS, CEBU-BALAMBAN-TRANSCENTRAL HIGHWAY, SEC.1: K0037+980-K0038+540.09, CEBU PROVINCE

REHABILITATION/RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE SECONDARY ROADS, CEBU-BALAMBAN-TRANSCENTRAL HIGHWAY, SEC.1: K0037+980-K0038+540.09, CEBU PROVINCE is a DPWH-tracked public work in Region VII, Region VII. Reported contract value: ₱139,620,000.00. Status: Reported complete (DPWH). Contractor on record: GRACE CONST CORP. Figures trace to dpwh.

Region VII, Region VII
Region: Region VII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2016 GAA. DBM GAA FY2016

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱139,620,000.00

Progress

Reported complete (DPWH)

Start Date

August 7, 2016

Target End

October 26, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.