Buildings and Facilities17FN0049

CONSTRUCTION OF ONE (1) STOREY TWO (2) CLASSROOM SCHOOL BUILDING (SITE 1), AT COLACLING ELEMENTARY SCHOOL, LUPI, CAMARINES SUR

CONSTRUCTION OF ONE (1) STOREY TWO (2) CLASSROOM SCHOOL BUILDING (SITE 1), AT COLACLING ELEMENTARY SCHOOL, LUPI, CAMARINES SUR is a DPWH-tracked public work in Camarines Sur 1st DEO, Region V. Reported contract value: ₱2,855,431.00. Status: Reported complete (DPWH). Contractor on record: A B OPENA BUILDERS. Figures trace to dpwh.

Camarines Sur 1st DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱3,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control, Brgy. La Medalla, Baao, Camarines Sur
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Agency-level releases for FY2017, not tied to this contract

Camarines Sur 1st DEO · SARO 1,101 (₱106,257,715,220.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱2,855,431.00

Progress

Reported complete (DPWH)

Start Date

September 15, 2017

Target End

December 8, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.