Roads20LC0112

CONCRETING OF PUROK 5 TO PUROK 8, BRGY. PANTARON FMR, BRGY. PANTARON, STO. TOMAS, DAVAO DEL NORTE

CONCRETING OF PUROK 5 TO PUROK 8, BRGY. PANTARON FMR, BRGY. PANTARON, STO. TOMAS, DAVAO DEL NORTE is a DPWH-tracked public work in Davao del Norte DEO, Region XI. Reported contract value: ₱9,910,200.29. Status: Reported complete (DPWH). Contractor on record: AB APONESTO CONST PARTS AND SUPPLY INC 22998. Figures trace to dpwh.

Davao del Norte DEO, Region XI
Region: Region XI

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱9,910,200.29

Progress

Reported complete (DPWH)

Start Date

October 14, 2020

Target End

January 16, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.