Buildings and Facilities19JE0094

CONSTRUCTION OF COVERED COURT, BRGY. LOWER SIBATANG, PAGADIAN CITY, ZAMBOANGA DEL SUR

CONSTRUCTION OF COVERED COURT, BRGY. LOWER SIBATANG, PAGADIAN CITY, ZAMBOANGA DEL SUR is a DPWH-tracked public work in Zamboanga del Sur 1st DEO, Region IX. Reported contract value: ₱2,468,847.51. Status: Reported complete (DPWH). Contractor on record: JIMWEN CONST. Figures trace to dpwh.

Zamboanga del Sur 1st DEO, Region IX
Region: Region IX

Money Trail

1. Appropriation

GAA FY2019 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

315 projects · ₱2.7B total · 0 flags

4. Implementation

Contract Amount

₱2,468,847.51

Progress

Reported complete (DPWH)

Start Date

September 2, 2019

Target End

November 30, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.