Roads16ED0020

CONCRETING OF DULANGAN I - DULANGAN III ROAD LEADING TO LANTUYAN RIVER, TOURISM SITE, BACO, ORIENTAL MINDORO

CONCRETING OF DULANGAN I - DULANGAN III ROAD LEADING TO LANTUYAN RIVER, TOURISM SITE, BACO, ORIENTAL MINDORO is a DPWH-tracked public work in Mindoro Oriental DEO, Region IV-B. Reported contract value: ₱4,679,400.24. Status: Reported complete (DPWH). Contractor on record: MARCPHIL CONST OPC FORMERLY: MARCPHIL CONST. Figures trace to dpwh.

Mindoro Oriental DEO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Mag - Asawang Tubig and Allied Rivers Flood Mitigation/Control Projects, Rehabilitation/Construction of Gabion Revetment at Naujan (Mag - Asawang Tubig), Mindoro Oriental
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-16-0001091

₱98,182.00 · FY2016

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱4,679,400.24

Progress

Reported complete (DPWH)

Start Date

April 5, 2016

Target End

May 10, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.