Buildings and Facilities17BG0177

CONSTRUCTION OF ONE (1) STOREY 1 UNIQUE TVL BUILDING (WITH 50 KVA SINGLE PHASE TRANSFORMER AND ELECTRIC POST) SAN ANTONIO NATIONAL HIGH SCHOOL, CITY OF CAUAYAN, ISABELA, SCHOOL ID NO. 300589

CONSTRUCTION OF ONE (1) STOREY 1 UNIQUE TVL BUILDING (WITH 50 KVA SINGLE PHASE TRANSFORMER AND ELECTRIC POST) SAN ANTONIO NATIONAL HIGH SCHOOL, CITY OF CAUAYAN, ISABELA, SCHOOL ID NO. 300589 is a DPWH-tracked public work in Isabela 3rd DEO, Region II. Reported contract value: ₱3,570,927.26. Status: Reported complete (DPWH). Contractor on record: D A CADELIÑA CONST. Figures trace to dpwh.

Isabela 3rd DEO, Region II
Region: Region II

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱5,500,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control / Drainage, Centro 2, Angadanan, Isabela
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVI-17-0020406

₱-18,489,950.00 · FY2017

Released to Iloilo 4th District Engineering Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

126 projects · ₱1.4B total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF NEMMATAN FLOOD CONTROL STRUCTURE, SECTION 1, SAN AGUS

Isabela 4th DEO, Region II

2025₱106.1M
Past target date (DPWH On-Going)

LOCAL PROGRAM - CONSTRUCTION / REPAIR / REHABILITATION / IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS - FLOOD CONTROL STRUCTURE/FACILITIES - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG CAGAYAN RIVER BANK - BRGY. PAPPAT, ANGADANAN, ISA

Isabela 3rd DEO, Region II

2021₱96.5M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT - ROAD WIDENING - PRIMARY ROADS - SANTIAGO-TUGUEGARAO ROAD - K0345+000 - K0346+825, SAN MATEO, ISABELA

Isabela 3rd DEO, Region II

2019₱48.5M
Reported complete (DPWH)
No sat.

OO1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - PRIMARY ROADS - SANTIAGO-TUGUEGARAO RD - K0362+614 - K0363+725, CABATUAN, ISABELA

Isabela 3rd DEO, Region II

2022₱44.5M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - SANTIAGO CIRCUMFERENTIAL ROAD, ISABELA

Isabela 4th DEO, Region II

2023₱39.4M
Reported complete (DPWH)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT - ROAD WIDENING - PRIMARY ROADS - SANTIAGO - TUGUEGARAO RD - K0348 + 943 - K0350 + 000 , SAN MATEO, ISABELA

Isabela 3rd DEO, Region II

2021₱35.0M
Reported complete (DPWH)
View all 126 projects →

4. Implementation

Contract Amount

₱3,570,927.26

Progress

Reported complete (DPWH)

Start Date

December 4, 2017

Target End

March 3, 2018

5. Audit