Flood Control and Drainage20FF0078

RIPRAPPING BRGY. STO. NIÑO QUIPAYO CALABANGA CAMARINES SUR

RIPRAPPING BRGY. STO. NIÑO QUIPAYO CALABANGA CAMARINES SUR is a DPWH-tracked public work in Camarines Sur 3rd DEO, Region V. Reported contract value: ₱2,825,521.60. Status: Reported complete (DPWH). Contractor on record: PBL BUILDERS. Figures trace to dpwh.

Camarines Sur 3rd DEO, Region V
Region: Region V

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱2,825,521.60

Progress

Reported complete (DPWH)

Start Date

October 16, 2020

Target End

May 22, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.