Love the Philippines

Anomaly / indicator worth examining — not an accusation.

Ito ay istatistikong anomalya o indikador na dapat suriin — hindi patunay ng maling gawain, pandaraya, o katiwalian laban sa sinumang tao.

AI-verified / Na-verify ng AI Data as of October 21, 2026

Schedule / Date Anomalies

Completion before start, implausible duration for cost, or future dates marked complete.

This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.

Indicator: contract 23AJ0012 (₱19.21M) is recorded as completed in 39 days against 162 planned; similar-cost projects take a median of 182 days, putting it in the fastest 0.8%. The contractor may have deployed extra resources or worked overtime to finish ahead of schedule.

Public record entityConstruction of Slope Protection Works along San Juan River, Barangay Turac, San Carlos City, Pangasinan (Phase II)
LocationSAN CARLOS CITY (PANGASINAN), PANGASINAN, Region IContract 23AJ0012
Amount₱19,212,536.57 sumbong source

Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.

Satellite before / after

Loading satellite imagery…

Project completion

Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.

Reported complete (DPWH): 1Ongoing: 0Delayed: 0Status unknown: 0
ProjectProg.Target endActual endDays lateStatus
Construction of Slope Protection Works along San Juan River, Barangay Turac, San Carlos City, Pangasinan (Phase II)23AJ0012Flood control100%July 25, 2023March 24, 2023—completedsumbong source

Start: February 13, 2023 · Source fetched October 21, 2026

Rule Definition

Compares start, target, and actual dates from Sumbong with contract cost.

Triggering Data & citations

Contract schedule fields are inconsistent or implausible

{
  "issues": [
    "implausibly_short_duration"
  ],
  "startDate": "2023-02-13T00:00:00.000Z",
  "contractId": "23AJ0012",
  "actualEndDate": "2023-03-24T00:00:00.000Z",
  "targetEndDate": "2023-07-24T00:00:00.000Z",
  "contractCostPhp": 19212536.57
}

Possible Innocent Explanations

  • Revised dates not yet reflected in Sumbong export
  • Early completion certificate vs planned start typo