Schedule / Date Anomalies
Completion before start, implausible duration for cost, or future dates marked complete.
This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.
Indicator: contract 23AJ0012 (₱19.21M) is recorded as completed in 39 days against 162 planned; similar-cost projects take a median of 182 days, putting it in the fastest 0.8%. The contractor may have deployed extra resources or worked overtime to finish ahead of schedule.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Satellite before / after
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.
| Project | Prog. | Target end | Actual end | Days late | Status |
|---|---|---|---|---|---|
| Construction of Slope Protection Works along San Juan River, Barangay Turac, San Carlos City, Pangasinan (Phase II)23AJ0012Flood control | 100% | July 25, 2023 | March 24, 2023 | — | completedsumbong source |
Start: February 13, 2023 · Source fetched October 21, 2026
Rule Definition
Compares start, target, and actual dates from Sumbong with contract cost.
Triggering Data & citations
Contract schedule fields are inconsistent or implausible
{
"issues": [
"implausibly_short_duration"
],
"startDate": "2023-02-13T00:00:00.000Z",
"contractId": "23AJ0012",
"actualEndDate": "2023-03-24T00:00:00.000Z",
"targetEndDate": "2023-07-24T00:00:00.000Z",
"contractCostPhp": 19212536.57
}Source documents
Possible Innocent Explanations
- Revised dates not yet reflected in Sumbong export
- Early completion certificate vs planned start typo