Roads23K00196

PREVENTIVE MAINTENANCE - SECONDARY ROADS , CDO - AIRPORT - BUKIDNON RD, K1440 + 900 - K1441 + 263, K1442 + 968 - 1443 + 171, K1444 + 000 - K1444 + 958, K1459 + 440 - K1460 + 000, K1462 + 800 - K1464 + 000, K1465 + 662 - K1466 + 262, (WITH EXCEPTION)

PREVENTIVE MAINTENANCE - SECONDARY ROADS , CDO - AIRPORT - BUKIDNON RD, K1440 + 900 - K1441 + 263, K1442 + 968 - 1443 + 171, K1444 + 000 - K1444 + 958, K1459 + 440 - K1460 + 000, K1462 + 800 - K1464 + 000, K1465 + 662 - K1466 + 262, (WITH EXCEPTION) is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱234,002,034.61. Status: Reported complete (DPWH). Contractor on record: NORTHERN BUILDERS. Figures trace to dpwh.

Region X, Region X
Region: Region X

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2023 GAA. DBM GAA FY2023

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱234,002,034.61

Progress

Reported complete (DPWH)

Start Date

April 11, 2023

Target End

December 7, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.