Flood Control and Drainage24CC0177

CONSTRUCTION/IMPROVEMENT OF FLOOD MITIGATION STRUCTURE AT ABULALAS, HAGONOY, BULACAN

CONSTRUCTION/IMPROVEMENT OF FLOOD MITIGATION STRUCTURE AT ABULALAS, HAGONOY, BULACAN is a DPWH-tracked public work in Bulacan 1st DEO, Region III. Reported contract value: ₱77,199,664.74. Status: Reported complete (DPWH). Contractor on record: 11-16 CONST. Figures trace to dpwh.

Bulacan 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Bagbag Creek, Barangay Pritil, Guiguinto, Bulacan
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-NCR-24-0000335

₱29,019,605.00 · FY2024

Released to Regional Office - NCR (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

244 projects · ₱19.8B total · 8 flags

4. Implementation

Contract Amount

₱77,199,664.74

Progress

Reported complete (DPWH)

Start Date

February 28, 2024

Target End

October 24, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.