Roads24F00331

CONCRETING OF BRGY. II, FMR BRGY. II, DAET, CAMARINES NORTE, DAET, CAMARINES NORTE (2ND LEGISLATIVE DISTRICT)

CONCRETING OF BRGY. II, FMR BRGY. II, DAET, CAMARINES NORTE, DAET, CAMARINES NORTE (2ND LEGISLATIVE DISTRICT) is a DPWH-tracked public work in Region V, Region V. Reported contract value: ₱9,649,905.84. Status: Past target date (DPWH On-Going). Contractor on record: ARIK CONST. Figures trace to dpwh.

Region V, Region V
Region: Region V

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2024 GAA. DBM GAA FY2024

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱9,649,905.84

Progress

Past target date (DPWH On-Going)

Start Date

April 3, 2025

Target End

August 19, 2025