Roads22PM0012

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT - PAVING OF UNPAVED ROADS - TERTIARY ROADS - JCT TALUBIN-BARLIG-NATONIN-PARACELIS-CALACCAD RD - (S04030LZ) CHAINAGE 3415 - CHAINAGE 4015

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT - PAVING OF UNPAVED ROADS - TERTIARY ROADS - JCT TALUBIN-BARLIG-NATONIN-PARACELIS-CALACCAD RD - (S04030LZ) CHAINAGE 3415 - CHAINAGE 4015 is a DPWH-tracked public work in Mountain Province 2nd DEO, Cordillera Administrative Region. Reported contract value: ₱21,560,000.00. Status: Reported complete (DPWH). Contractor on record: 4RMCONSTRUCTION. Figures trace to dpwh.

Mountain Province 2nd DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Katao Flood Control Structure, Sta. 085 + 870, Brgy. Buringal, Paracelis, Mountain Province
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-C-22-0007714

₱25,390,000.00 · FY2022

Released to Central Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

17 projects · ₱174.1M total · 0 flags

4. Implementation

Contract Amount

₱21,560,000.00

Progress

Reported complete (DPWH)

Start Date

May 26, 2022

Target End

December 25, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.