GAA 2016 Locally Funded Projects15JF0068

REHAB. OF THE APPROACHES OF KALIANTANA BRIDGE, NAGA, ZS

REHAB. OF THE APPROACHES OF KALIANTANA BRIDGE, NAGA, ZS is a DPWH-tracked public work in Zamboanga Sibugay 2nd DEO, Region IX. Reported contract value: ₱47,995,044.23. Status: Reported complete (DPWH). Contractor on record: LONG ISLAND BUILDERS. Figures trace to dpwh.

Zamboanga Sibugay 2nd DEO, Region IX
Region: Region IX

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱38,800,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Flood Control Structure along Tungawan River - Improvement/Repair/Maintenance of Flood Control along Lanao - Pagadian - Zamboanga City Road, K1840+064, Upper Tungawan Bridge, Tungawan, Zamboanga Sibugay
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-D-16-0000211

₱200,000.00 · FY2016

Released to Central Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

275 projects · ₱5.6B total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG PULIRAN RIVER, PULIRAN BR. SECTION PACKAGE 2, SIBUCO, ZAMBOANGA DEL NORTE

Region IX, Region IX

2024₱164.0M
Past target date (DPWH On-Going)
No sat.

ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - REHABILITATION OF ROAD, BARANGAY BALAKAN-BARANGAY CALUCAP ROAD, SALUG, ZAMBOANGA DEL NORTE

Region IX, Region IX

2025₱153.0M
Past target date (DPWH On-Going)

CONSTRUCTION / REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SIOCON RIVER (DOWNSTREAM), SIOCON, ZAMBOANGA DEL NORTE, PACKAGE 2

Region IX, Region IX

2024₱137.9M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SALUG RIVER AT SALUG BR. SECTION (B00528MN) ALONG SINDANGAN-LILOY ROAD (S01142MN), SALUG, ZAMBOANGA DEL NORTE, PACKAGE 1

Region IX, Region IX

2024₱128.8M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE WITH ESPLANADE AT SALUG BRIDGE (B00528MN), SALUG, ZAMBOANGA DEL NORTE

Region IX, Region IX

2023₱109.9M
Past target date (DPWH On-Going)

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG KIPIT RIVER, GUTALAC, ZAMBOANGA DEL NORTE (UPSTREAM) STA. 0 + 204 - 0 + 604

Zamboanga del Norte 3rd DEO, Region IX

2024₱95.5M
Reported complete (100% progress, DPWH status On-Going)
View all 275 projects →

4. Implementation

Contract Amount

₱47,995,044.23

Progress

Reported complete (DPWH)

Start Date

February 23, 2016

Target End

October 27, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.