Roads25KB0011

CONSTRUCTION OF ROAD, BARANGAY POBLACION SUR, DON CARLOS, BUKIDNON

CONSTRUCTION OF ROAD, BARANGAY POBLACION SUR, DON CARLOS, BUKIDNON is a DPWH-tracked public work in Bukidnon 2nd DEO, Region X. Reported contract value: ₱9,850,908.24. Status: Past target date (DPWH On-Going). Contractor on record: MAFIL BUILDERS INC. Figures trace to dpwh.

Bukidnon 2nd DEO, Region X
Region: Region X

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure, Barangay Miglamin, Malaybalay City, Bukidnon
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROV-25-0006579

₱976,709.00 · FY2025

Released to Bonga National High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

Road

₱9,850,908.24 · MAFIL BUILDERS, .

Contractor

A

301 projects · ₱2.8B total · 0 flags

4. Implementation

Contract Amount

₱9,850,908.24

Progress

Past target date (DPWH On-Going)

Start Date

February 20, 2025

Target End

June 4, 2025

5. Audit