Buildings and Facilities22CC0273

CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BRGY. BAGONG NAYON, BALIUAG, BULACAN

CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BRGY. BAGONG NAYON, BALIUAG, BULACAN is a DPWH-tracked public work in Bulacan 1st DEO, Region III. Reported contract value: ₱9,899,146.84. Status: Reported complete (DPWH). Contractor on record: EIRISH BUILDERS. Figures trace to dpwh.

Bulacan 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Brgy. Pagala, Baliuag, Bulacan
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-NCR-22-0004772

₱32,843,607.00 · FY2022

Released to Regional Office - NCR (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

126 projects · ₱3.4B total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRA. PROJECTS ALLEVIATING GAPS(SIPAG)-SIPAG-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONST. OF ROAD,PHASE II,SITIO TALAMSI I-SITIO KAMB

Bulacan 3rd DEO, Region III

2025₱142.5M
Past target date (DPWH On-Going)
No sat.

CONVERGE. AND SPECIAL SUPPORT PROG. - SUSTAINABLE INFRA. PROJS. ALLEVIATING GAPS (SIPAG) - SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/ STRAT. PUBLIC BLDGSS/ FACILITIES - CONST.OF ROAD, PHASE I, SITIO TALAMSI I - SITIO KAM

Bulacan 3rd DEO, Region III

2025₱142.5M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF MULTI-PURPOSE BUILDING (NEW MUNICIPAL HALL), ANGAT, BULACAN

Bulacan 2nd DEO, Region III

2023₱117.5M
Reported complete (DPWH)
No sat.

STATE UNIVERSITIES AND COLLEGES (SUCS)-ESTABLISHMENT AND/OR SUPPORT TO THE COLLEGE OF MEDICINES, SAN RAFAEL CAMPUS-BULACAN STATE UNIVERSITY, SAN RAFAEL, BULACAN, PROVINCE OF BULACAN

Region III, Region III

2024₱98.5M
Past target date (DPWH On-Going)

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG MEYCAUAYAN RIVER, LONGOS - ZAMORA SECTION, STA. 06+220 - STA. 06+340, MEYCAUAYAN, BULACAN

Bulacan 2nd DEO, Region III

2025₱96.5M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONSTRUCTION OF MULTI-PURPOSE BUILDING, CITY COLLEGE OF SAN JOSE DEL MONTE SCHOOL OF NURSING AND ALLIED HEALTH (PHASE 2), BARANGAY MINUYAN PROPER, CITY OF SAN JOSE DEL MONTE, BULACAN

Bulacan 2nd DEO, Region III

2025₱96.0M
Past target date (DPWH On-Going)
View all 126 projects →

4. Implementation

Contract Amount

₱9,899,146.84

Progress

Reported complete (DPWH)

Start Date

April 6, 2022

Target End

October 2, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.