CONCRETING OF BARANGAY TENAN-BACALAN FMR(PHASE II) IPIL, Z.S.

CONCRETING OF BARANGAY TENAN-BACALAN FMR(PHASE II) IPIL, Z.S. is a DPWH-tracked public work in Zamboanga Sibugay 2nd DEO, Region IX. Reported contract value: ₱9,639,945.82. Status: Reported complete (DPWH). Contractor on record: DIPLAHAN COMMERCIAL AND CONST. Figures trace to dpwh.

Zamboanga Sibugay 2nd DEO, Region IX
Region: Region IX

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱31,340,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Flood Control Structure along Sibuguey River Basin - Rehabilitation/Improvement of flood control (Phase II) along Sibugay River Basin, Barangay Sibugay, Siay, Zamboanga Sibugay 2nd District
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-D-16-0000211

₱200,000.00 · FY2016

Released to Central Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱9,639,945.82

Progress

Reported complete (DPWH)

Start Date

February 23, 2016

Target End

June 4, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.