Flood Control and Drainage18ED0034

RESTORATION OF ALAG RIVER CONTROL APPROACH A DOWNSTREAM, BACO, ORIENTAL MINDORO

RESTORATION OF ALAG RIVER CONTROL APPROACH A DOWNSTREAM, BACO, ORIENTAL MINDORO is a DPWH-tracked public work in Mindoro Oriental DEO, Region IV-B. Reported contract value: ₱8,747,363.41. Status: Reported complete (DPWH). Contractor on record: CMSEL CONST. Figures trace to dpwh.

Mindoro Oriental DEO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

Probable match · score 97%

UACS
18001
Amount
₱9,300,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Restoration of Alag River Control Approach "A" Downstream, Baco, Oriental Mindoro
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-18-0009889

₱40,000,000.00 · FY2018

Released to Southern Mindoro District Engineering Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱8,747,363.41

Progress

Reported complete (DPWH)

Start Date

March 13, 2018

Target End

November 1, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.