Buildings and Facilities21AI0181

CONSTRUCTION/COMPLETION (2STY 4CL & 2STY 8 CL SCHOOL BUILDING), DOMANPOT ES, ASINGAN, PANGASINAN

CONSTRUCTION/COMPLETION (2STY 4CL & 2STY 8 CL SCHOOL BUILDING), DOMANPOT ES, ASINGAN, PANGASINAN is a DPWH-tracked public work in Pangasinan 3rd DEO, Region I. Reported contract value: ₱722,937.59. Status: Reported complete (DPWH). Contractor on record: A P TAGARINO ENGINEERING AND CONST SERVICES. Figures trace to dpwh.

Pangasinan 3rd DEO, Region I
Region: Region I

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱1,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Repair/ Rehabilitation of Mitura River Flood Control, Brgy. Sobol-Macalong, Asingan, Pangasinan
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROXI-21-0005464

₱490,751.00 · FY2021

Released to Davao Oriental 1st District Engineering Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱722,937.59

Progress

Reported complete (DPWH)

Start Date

September 27, 2021

Target End

October 26, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.