Buildings and Facilities16HE0073

CONSTRUCTION OF THREE (3) STOREY SIX (6) CLASSROOM SCHOOL BUILDING AT BIASONG ELEMENTARY SCHOOL, TALISAY CITY, CEBU

CONSTRUCTION OF THREE (3) STOREY SIX (6) CLASSROOM SCHOOL BUILDING AT BIASONG ELEMENTARY SCHOOL, TALISAY CITY, CEBU is a DPWH-tracked public work in Cebu 1st DEO, Region VII. Reported contract value: ₱11,265,346.04. Status: Reported complete (DPWH). Contractor on record: LCTING CONST AND DEVELOPMENT CORP FORMERLY: L C TING CONST. Figures trace to dpwh.

Cebu 1st DEO, Region VII
Region: Region VII

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱16,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Drainage/Facilities, Cebu North Hagnaya Wharf Road, Bogo City, Cebu, K0093+304 - K0094+195, K0099+017 - K0100+180
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-16-0012921

₱37,245,074.00 · FY2016

Released to Division of Biliran (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱11,265,346.04

Progress

Reported complete (DPWH)

Start Date

February 20, 2017

Target End

July 19, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.