GAA 2023 CSSP23FN0027

CSSP: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES - CONSTRUCTION OF BANK PROTECTION STRUCTURE, BRGY. SANTA JUSTINA, BUHI, CAMARINES SUR

CSSP: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES - CONSTRUCTION OF BANK PROTECTION STRUCTURE, BRGY. SANTA JUSTINA, BUHI, CAMARINES SUR is a DPWH-tracked public work in Camarines Sur 5th DEO, Region V. Reported contract value: ₱96,412,799.29. Status: Reported complete (DPWH). Contractor on record: HI-TONE CONST. Figures trace to dpwh.

Camarines Sur 5th DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure, Brgy. Sibobo (Zone 5), Calabanga, Camarines Sur
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROII-23-0026851

₱-35,138,256.00 · FY2023

Released to 0000000 Nueva Vizcaya State - University (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

555 projects · ₱31.0B total · 0 flags

4. Implementation

Contract Amount

₱96,412,799.29

Progress

Reported complete (DPWH)

Start Date

February 17, 2023

Target End

February 6, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.