GAA 2016 MFO-116I00048

REHAB./RECONST./UPGRADING OF DAMAGED PAVED NATIONAL ROADS INCLUDING DRAINAGE BASED ON PMS/HDM-4, MARIPIPI CIRCUMFERENTIAL ROAD, KO000+450 - KO003+120; KO018+200 - KO021+500, MARIPIPI, BILIRAN

REHAB./RECONST./UPGRADING OF DAMAGED PAVED NATIONAL ROADS INCLUDING DRAINAGE BASED ON PMS/HDM-4, MARIPIPI CIRCUMFERENTIAL ROAD, KO000+450 - KO003+120; KO018+200 - KO021+500, MARIPIPI, BILIRAN is a DPWH-tracked public work in Region VIII, Region VIII. Reported contract value: ₱128,881,601.84. Status: Reported complete (DPWH). Contractor on record: PREMIUM MEGASTRUCTURES INC. Figures trace to dpwh.

Region VIII, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2016 GAA. DBM GAA FY2016

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱128,881,601.84

Progress

Reported complete (DPWH)

Start Date

July 6, 2016

Target End

August 20, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.