Roads18K00200

CLUSTER 3 CONSTRUCTION OF MISSING LINKS/ NEW ROADS, BUKIDNON

CLUSTER 3 CONSTRUCTION OF MISSING LINKS/ NEW ROADS, BUKIDNON is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱276,376,238.77. Status: Reported complete (DPWH). Contractor on record: PREMIUM MEGASTRUCTURES INC. Figures trace to dpwh.

Region X, Region X
Region: Region X

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2018 GAA. DBM GAA FY2018

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱276,376,238.77

Progress

Reported complete (DPWH)

Start Date

July 12, 2018

Target End

June 5, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.