Buildings and Facilities17AI0503

CONSTN OF TWO STRY FOUR CL SB AT SAN JOSE E/S, NATIVIDAD, PANGASINAN

CONSTN OF TWO STRY FOUR CL SB AT SAN JOSE E/S, NATIVIDAD, PANGASINAN is a DPWH-tracked public work in Pangasinan 3rd DEO, Region I. Reported contract value: ₱9,556,523.46. Status: Reported complete (DPWH). Contractor on record: PHESCO INC 145. Figures trace to dpwh.

Pangasinan 3rd DEO, Region I
Region: Region I

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Agno River Basin and Allied Rivers Flood Control Project-Construction of Bank Protection, Brgy. Baligayan, San Quintin, Pangasinan
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXI-17-0020284

₱2,411,974.00 · FY2017

Released to University of Southeastern Philippines (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

342 projects · ₱29.0B total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - BRIDGE PROGRAM - REPLACEMENT OF PERMANENT WEAK BRIDGES SOOT BRIDGE (B00989LZ) ALONG ABRA - ILOCOS NORTE ROAD

Cordillera Administrative Region, Cordillera Administrative Region

2020₱530.8M
Reported complete (DPWH)
No sat.

CLUSTER: ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS GOV. BADO DANGWA NATIONAL ROAD (1) K0342 +

Cordillera Administrative Region, Cordillera Administrative Region

2021₱492.1M
Reported complete (DPWH)
No sat.

ROCKFALL NETTING INCLUDING IMPROVEMENT OF CRITICAL INTERSECTION AT JCT. SHRINE HILLS ALONG DAVAO CITY DIVERSION ROAD, MATINA CROSSING, DAVAO CITY

Region XI, Region XI

2021₱333.7M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS - CONG. ANDRES ACOP COSALAN RD, KO301+(-905) - KO304+024, KO313+175 - KO317+533, KO319+000 - KO322+600, KO324+0

Cordillera Administrative Region, Cordillera Administrative Region

2022₱289.5M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS BENGUET - NUEVA VIZCAYA ROADKO254+(-372) - KO281+800BENGUET

Cordillera Administrative Region, Cordillera Administrative Region

2021₱289.5M
Reported complete (DPWH)
No sat.

MT PROV - CAGAYAN VIA TABUK - ENRILE RD, K0406+453 - KO406+692SADANGA, MT. PROVINCE

Cordillera Administrative Region, Cordillera Administrative Region

2022₱289.5M
Reported complete (DPWH)
View all 342 projects →

4. Implementation

Contract Amount

₱9,556,523.46

Progress

Reported complete (DPWH)

Start Date

December 20, 2017

Target End

July 27, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.