Roads24DP0095

ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS - CALAUAN-NAGCARLAN BDRY RD - K0088 + 535 - K0088 + 581

ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS - CALAUAN-NAGCARLAN BDRY RD - K0088 + 535 - K0088 + 581 is a DPWH-tracked public work in Laguna 3rd DEO, Region IV-A. Reported contract value: ₱38,904,989.87. Status: Past target date (DPWH On-Going). Contractor on record: N D M SANCHEZ BUILDERS. Figures trace to dpwh.

Laguna 3rd DEO, Region IV-A
Region: Region IV-A

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure for Masapang Br. 1 ( B02881LZ ) , Victoria, Laguna
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-D-24-0003323

₱41,453,000.00 · FY2024

Released to Laguna 3rd DEO (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

188 projects · ₱4.0B total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF MULTI-PURPOSE BUILDING, ROSARIO, BATANGAS

Region IV-A, Region IV-A

2025₱194.1M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. CASTILLO, PADRE GARCIA, BATANGAS

Batangas 4th DEO, Region IV-A

2024₱115.2M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), COASTAL ROADS TO AUGMENT RESILIENCY OF COASTAL COMMUNITIES, IMPROVEMENT OF BAUAN - MABINI CIRCUMFERENTIAL ROAD, BARANGAY SAN JUAN, MAINAGA SECTION, MABI

Batangas 2nd DEO, Region IV-A

2025₱114.6M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. SAN SEBASTIAN, MATAAS NA KAHOY, BATANGAS

Batangas 3rd DEO, Region IV-A

2023₱99.0M
Past target date (DPWH On-Going)
No sat.

CSSP - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI PURPOSE BUILDING (PAMANTASAN NG LUNGSOD NG SAN PABLO), BRGY SAN JOSE, SAN PABLO CITY, LAGUNA

Laguna 3rd DEO, Region IV-A

2025₱96.5M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING (PUBLIC MARKET), ROSARIO, BATANGAS, PHASE 2

Batangas 4th DEO, Region IV-A

2023₱93.6M
Reported complete (DPWH)
View all 188 projects →

4. Implementation

Contract Amount

₱38,904,989.87

Progress

Past target date (DPWH On-Going)

Start Date

June 11, 2024

Target End

April 19, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.