Roads23DB0024

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ROAD, LIAN, BATANGAS

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF ROAD, LIAN, BATANGAS is a DPWH-tracked public work in Batangas 1st DEO, Region IV-A. Reported contract value: ₱5,938,760.00. Status: Reported complete (DPWH). Contractor on record: W RIVERA CONST AND EQUIPT RENTALS INC FORMERLY: W RIVERA CONST. Figures trace to dpwh.

Batangas 1st DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱6,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure in the Municipality of Lemery, Batangas
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-23-0025019

₱1,055,575.00 · FY2023

Released to 0300005 Regional Office -V - (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

102 projects · ₱1.1B total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE FACILITY (COLISEUM) AT PANSOL, POBLACION 4, BAUAN, BATANGAS

Batangas 2nd DEO, Region IV-A

2023₱108.9M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), EVACUATION CENTERS/QUARANTINE FACILITIES/PUBLIC HEALTH FACILITIES, CONSTRUCTION OF MULTI-PURPOSE BUILDING (COMMUNITY CENTER), SAN ISIDRO EVACUATION COMPLEX, BATANGAS CITY, BATANG

Batangas 2nd DEO, Region IV-A

2023₱49.5M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), EVACUATION CENTERS/QUARANTINE FACILITIES/PUBLIC HEALTH FACILITIES, CONSTRUCTION OF MULTI-PURPOSE BUILDING AT SAN ISIDRO EVACUATION COMPLEX, BATANGAS CITY, BATANGAS

Batangas 2nd DEO, Region IV-A

2023₱49.5M
Reported complete (DPWH)
No sat.

LOCAL PROGRAM - CONSTRUCTION OF MULTI-PURPOSE BUILDING, POBLACION 4, BAUAN, BATANGAS

Batangas 2nd DEO, Region IV-A

2021₱39.6M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT

Batangas 2nd DEO, Region IV-A

2020₱39.2M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF EVACUATION CENTER AT BRGY. LAUREL, SAN PASCUAL, BATANGAS PROVINCE

Region IV-A, Region IV-A

2018₱34.0M
Reported complete (DPWH)
View all 102 projects →

4. Implementation

Contract Amount

₱5,938,760.00

Progress

Reported complete (DPWH)

Start Date

February 7, 2023

Target End

May 7, 2023

5. Audit