Flood Control and Drainage24CK0179

CONSTRUCTION OF GROUNDSILL WITH REINFORCED CONCRETE SLOPE PROTECTION ALONG PARUA RIVER, DOWNSTREAM OF SANTA RITA BRIDGE, PHASE 2, CONCEPCION, TARLAC

CONSTRUCTION OF GROUNDSILL WITH REINFORCED CONCRETE SLOPE PROTECTION ALONG PARUA RIVER, DOWNSTREAM OF SANTA RITA BRIDGE, PHASE 2, CONCEPCION, TARLAC is a DPWH-tracked public work in Tarlac 2nd DEO, Region III. Reported contract value: ₱72,372,314.69. Status: Reported complete (DPWH). Contractor on record: GVDPM CONST CORP FORMERLY: ZM CONSTRUCTIO. Figures trace to dpwh.

Tarlac 2nd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Structure along Ungot Creek ( Segment U ) , Tarlac City, Tarlac
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXIII-24-0010947

₱9,313,260.00 · FY2024

Released to Division of Tandag City (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

166 projects · ₱9.9B total · 2 flags

Other projects by this contractor

No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS-PRIMARY ROADS - MANILA NORTH RD - K0595 + 000 - K0599 + 810; K0600 + 000 - K0600 + 979.7; K0680+000 - K0682+000; K0684+

Region II, Region II

2024₱224.7M
Past target date (DPWH On-Going)
No sat.

NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF MISSING LINKS/NEW ROADS, CAPAS-BOTOLAN ROAD (BUENO BRIDGE 1), PROVINCE OF TARLAC

Region III, Region III

2021₱214.2M
Reported complete (DPWH)
No sat.

OO1: ENSURE SAFE & RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING- PRIMARY ROADS - MANILA NORTH RD - K0601 + 074 - K0602 + 349, K0602 + 421 - K0603 + 724, K0611 + 1109 - K0612 +729

Region II, Region II

2024₱204.4M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF MISSING GAPS CONNECTING NR, INCLUDING ROW, CAPAS-BOTOLAN ROAD (ZAMBALES SECTION), INCLUDING ROW, ZAMBALES, PROVINCE OF ZAMBALES

Region III, Region III

2017₱188.0M
Reported complete (DPWH)
No sat.

CONSTRUCTION & MAINTENANCE OF BRIDGES ALONG NATIONAL ROADS, WIDENING OF PERMANENT BRIDGES INCLUDING ROW, TO MORE THAN 2-LANES-BARANGOBONG BRIDGE-1 (BO1364LZ) ALONG PANIQUI-CAMILING-WAWA ROAD, TARLAC 1ST LEGISLATIVE DISTRICT PROVINCE OF TARLAC

Region III, Region III

2017₱165.1M
Reported complete (DPWH)
No sat.

NATIONAL ROAD AND BRIDGES-RECONSTRUCTION OF LABI BRIDGE ALONG NUEVA ECIJA-AURORA ROAD, BONGABON, NUEVA ECIJA, DAMAGED BY TYPHOON KABAYAN, LANDO AND NONA, PROVINCE OF NUEVA ECIJA

Region III, Region III

2016₱163.5M
Reported complete (DPWH)
View all 166 projects →

4. Implementation

Contract Amount

₱72,372,314.69

Progress

Reported complete (DPWH)

Start Date

December 6, 2024

Target End

June 7, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.