GAA 2025 OO-125A00125

WIDENING OF PERMANENT BRIDGES - SAN LUIS BR. 2 (B00831LZ) ALONG ROSARIO-PUGO RD (PHASE II)

WIDENING OF PERMANENT BRIDGES - SAN LUIS BR. 2 (B00831LZ) ALONG ROSARIO-PUGO RD (PHASE II) is a DPWH-tracked public work in Region I, Region I. Reported contract value: ₱14,029,998.87. Status: Past target date (DPWH On-Going). Contractor on record: KRYPTONITE 6S BUILDERS INC. Figures trace to dpwh.

Region I, Region I
Region: Region I

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2025 GAA. DBM GAA FY2025

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱14,029,998.87

Progress

Past target date (DPWH On-Going)

Start Date

April 7, 2025

Target End

July 5, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.