Construction of Flood Mitigation Structure25CE0056

Construction of Slope Protection Structure, Calinat Dam at PRIS SDC, Science City of Muñoz, Nueva Ecija

Construction of Slope Protection Structure, Calinat Dam at PRIS SDC, Science City of Muñoz, Nueva Ecija is a DPWH-tracked public work in SCIENCE CITY OF MUÑOZ (NUEVA ECIJA), NUEVA ECIJA, Region III. Reported contract value: ₱9,701,851.92. Status: Reported complete (DPWH). Contractor on record: IJK MAE CONST INC. Figures trace to sumbong.

SCIENCE CITY OF MUÑOZ (NUEVA ECIJA), NUEVA ECIJA, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱41,836,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Talavera River, Barangay Calipahan, Talavera, Nueva Ecija
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVI-25-0006663

₱81,000.00 · FY2025

Released to Jamabalud National High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-25-0007584

₱10,000,000.00 · FY2025

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-25-0000661

₱3,654,000.00 · FY2025

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-25-0010427

₱1,134,160.00 · FY2025

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-25-0019356

₱610,000.00 · FY2025

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-25-0000660

₱367,000.00 · FY2025

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-25-0008101

₱670,836,000.00 · FY2025

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

408 projects · ₱3.0B total · 3 flags

4. Implementation

Contract Amount

₱9,701,851.92

Progress

Reported complete (DPWH)

Start Date

February 11, 2025

Target End

May 11, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.