Roads19JE0078

CONCRETING OF BARANGAY ROAD, BARANGAY NEW VILLAGE, TAMBULIG, ZAMBOANGA DEL SUR.

CONCRETING OF BARANGAY ROAD, BARANGAY NEW VILLAGE, TAMBULIG, ZAMBOANGA DEL SUR. is a DPWH-tracked public work in Zamboanga del Sur 1st DEO, Region IX. Reported contract value: ₱9,404,990.45. Status: Reported complete (DPWH). Contractor on record: MG CONST. Figures trace to dpwh.

Zamboanga del Sur 1st DEO, Region IX
Region: Region IX

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIX-19-0019138

₱162,000.00 · FY2019

Released to Zamboanga del Sur National High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

213 projects · ₱1.4B total · 1 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 002: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS: FLOOD MANAGEMENT PROGRAM: CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS: CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG JAGONIPA RIVER (UPST

Negros Oriental 3rd DEO, Negros Island Region

2025₱72.3M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES / FACILITIES: CONSTRUCTION OF FLOOD CONTROL STRUCTURE (UPSTREAM), MAYABON, ZAMBOANGUITA

Negros Oriental 3rd DEO, Negros Island Region

2025₱48.9M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 001: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: ASSET PRESERVATION PROGRAM: CONSTRUCTION / UPGRADING / REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS : PRIMARY ROADS: DUMAGUETE SOUTH RD : K0033 + 518 - K0034 + 324, (K0033 + 0

Negros Oriental 3rd DEO, Negros Island Region

2024₱32.3M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/FACILITIES: CONSTRUCTION OF ROAD, TIMBAO - LIPTONG,

Negros Oriental 3rd DEO, Negros Island Region

2025₱29.3M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF WHITE COPRA (WHOLE NUT BUILDING), ZAMBOANGUITA, NEGROS ORIENTAL

Region VII, Region VII

2024₱26.3M
Reported complete (DPWH)
No sat.

DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM-TRIP) - ACCESS ROAD LEADING TO BRAVO GOLF COURSE, RESORT & SPA SIBULAN, PULANGBATO FALLS & TIERRA ALTA RESIDENTIAL RESORT, VALENCIA-BRGY. SAN SANTONIO, SIBULAN, NEGROS ORIENTAL

Negros Oriental 2nd DEO, Negros Island Region

2023₱24.5M
Reported complete (DPWH)
View all 213 projects →

4. Implementation

Contract Amount

₱9,404,990.45

Progress

Reported complete (DPWH)

Start Date

August 11, 2019

Target End

October 19, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.